Adani Enterprises Ltd announces highest half-yearly EBIDTA in H1FY25 results

Adani Enterprises Ltd (AEL), the flagship company of the Adani Group, announced its results today for the quarter and half year ended 30 September 2024.

AEL’s constant endeavour on achieving operational efficiency across all business verticals along with incubating new asset base is reflected yet again in these results. AEL has recorded its highest half-yearly EBIDTA of INR 8,654 crore which is consistently supported by strong performance from emerging core infra businesses under its incubation portfolio. The emerging core infra businesses has recorded half-yearly EBIDTA of INR 5,233 crore with an increase of 85% on year-on-year basis on back of robust operational performance.

“Adani Enterprises Ltd (AEL) continues to focus on investing in logistics, energy transition and adjacent sectors that are core to the economic growth of the country. This record-breaking half-year performance has been led by Adani New Industries Ltd (ANIL) and Adani Airport Holdings Ltd (AAHL) with their rapid growth in capacity additions and asset utilisation,” said Mr Gautam Adani, Chairman of the Adani Group. “Our focus on execution of greenfield projects in ANIL across three giga scale integrated manufacturing plants and the accelerated development of Navi Mumbai International Airport are driving these robust results. Further, AEL is poised to repeat this turbo growth across data centres, roads, metals & materials and specialized manufacturing. AEL continues to invest in innovative technology across its platforms to support this high growth phase.”

Consolidated Financial Highlights       

ParticularsQ2 FY24Q2 FY25% change Y-o-Y H1 FY24H1 FY25% change Y-o-Y
Total Income20,09523,19615% 43,111       49,26314%
EBIDTA2,9794,35446% 5,875         8,65447%
Profit Before Tax8792,409174% 1,959         4,644137%
Profit After Tax12281,7476.6x 903          3,2062.5x
Cash Accruals21,2422,972139% 2,735          5,677107%

Incubating Businesses Financial Highlights

                                                   ParticularsQ2 FY24Q2 FY25% change Y-o-Y H1 FY24H1 FY25% change Y-o-Y
ANIL Ecosystem    
Total Income1,9393,11560% 3,837          7,63499%
EBIDTA6281,12178% 983          2,763181%
PBT52691674% 801          2,341192%
Airports    
Total Income1,9462,27617% 3,657          4,45322%
EBIDTA56874431% 1,080          1,42632%
PBT(65)(148) (163)           (237)

Operational Highlights

VolumeQ2 FY24Q2 FY25% change Y-o-Y H1 FY24H1 FY25% change Y-o-Y
ANIL Ecosystem    
Module Sales (MW)630100159% 1244238091%
WTG (Sets)15#1 56#1
Airports    
Pax movement (Mn)21.322.35% 42.645.16%
ATMs (‘000)146.8153.34% 288.4305.46%
Cargo (Lacs MT)1.92.847% 4.25.531%
Roads    
Construction (L-KM)12.5180.413.4x 92.3910.48.8x
Mining Services    
Dispatch (MMT)6.28.232% 12.617.539%
IRM    
Volume (MMT)18.813.7(27%) 36.629.1(21%)
Capital market transactions
AEL has raised INR 4,200 crore (USD ~500 Mn) through QIP which was subscribed with participation from international and domestic investors AEL has raised INR 800 crore (USD ~100 Mn) through maiden public issuance of NCDs which is first public issue by any private corporate in last decade AEL’s airport arm AAHL has raised INR 1,950 crore (USD ~230 Mn) through issuance of NCDs with participation from Mutual Funds and Banks AEL’s road business arm ARTL’s SPVs has raised INR 1,124 crore (USD ~130 Mn) through issuance of AAA rated NCDs with structured maturities up to 11 years

Business Updates

Adani New Industries Ecosystem
Solar manufacturing Module sales cross 2 GW during first six months; export increased by 64% and domestic sale increased by 139%EBITDA margins continued to improve on account of improved realization and operational efficiency through integrated production of cell & module line
Wind Turbine manufacturing The 5.2 MW & 3.0 MW WTG using ANIL blades listed in RLMMFinal type certificate received for 3.3 MW WTG and applied for RLMM listing300th Blade production milestone crossed during this quarter
AdaniConnex Pvt Ltd (ACX – Data Centre)
Noida Data Centre Construction Completion ~95% of 50MW core & shell + 10 MW MEP
Hyderabad Data Centre Construction Completion ~98% for Phase I – 9.6 MW
Pune Data Centre Pune I ~38% and Pune II ~61% for Phase I – 9.6 MW